19 Sep Street, Wastewater Pipes and Tiles
In the last months we have mainly worked in the outer areas. The wastewater pipes have been conected and along the train tracks a wall was built to create room for the required parking places. Inside the tiles in the chemical production and coating room have been fitted.
Today the old NVA bunker residuals were crushed to build the new truck turning place.
When the new road is finished our strong forklift Bruno will come out and empty the southern storage so the water pipes can be fitted. After this the chemical production can move in.