Main slitter rebuild project or why we can´t make any 120 film at the moment

17.7.2018: The first part is finished.

5.10.2018: The antistatic components as well as all overhauled black rollers are back in place. New knife shafts and knives are in.

The web transport was overhauled and adjusted.

Only the knife shaft downholder is still in production. We try to make a first slitting despite next week on a thin base.

 

Januarry 2019: First Cuttings with filmbase to be coated in Marly.